BAM Construction - Hull University

Bam Construction - Hull University

LOCATION: Hull University Campus
SIZE: 250.0m x 2.40m (high). 1x Vehicle Access Gate.2x Pedestrian Access Gate.
HIRE DURATION: 52 Weeks
ERECTION DURATION: 1 Week
DESCRIPTION OF WORKS: Hull University required a large freestanding external hoarding to ensure that no public or students would interfere with the works being carried out. HoardTek were asked to construct a hoarding that did not penetrate the ground and ensured that little would have to be done to correct the work after the hoarding was dismantled.
MATERIALS: 100% recycled uPVC external cladding panels. 750KG ‘Lego’ style Kentlege blocks.
COMMENTS: A full scaffold design was provided.