Pricebusters, Blackpool

Pricebusters

Project Name – Pricebusters, Blackpool

Main Contractor – Stoneguard

Works – HT were contracted to provide general access scaffold for terracotta and window repairs. The main contractor brief was to erect the scaffold out of normal working hours and supply only 25% of the material with this to be stripped and re-erected around the building in phases.

Materials - The project required conventional tube and fitting scaffold materials.

Design – The design had to take into account a seven day tight working program and very high wind loads as the building was adjacent to the sea.

Comments –