Project Name – Lyme Hall (National Trust)

Main Contractor – William Anelay Building and Restoration Contractors

Works – HT were contracted to provide a full external access scaffold and temporary roof over the full building to undertake external façade works and a compete new roof.

Materials – The project required Conventional and system scaffold with 750mm deep Haki beams.

Design – The design of this structure was complicated with huge spine beams having to be manually erected. It was imperative that the roof was 100% watertight to protect the ornate ceilings located below. The roof was erected using the revolutionary new Kadar Roof sheets.

Comments